AI data centers: why electricity now sets the pace of AI
The DOE projects US data center electricity demand will double or triple by 2028, and the queue to connect the new power they need is already years long.
- US data centers of all types used 4.4% of US electricity in 2023; the DOE projects 6.7-12% by 2028.
- Only about 1 in 5 projects that requested a US grid connection from 2000 to 2020 had reached commercial operation by the end of 2025.
- FERC rejected a hyperscaler's co-location upgrade 2-1 in Nov 2024, and voters in 40 of 41 local ballot initiatives voted to limit or block data centers.
A new AI model generation takes weeks to months to build. A new connection to the power grid took a median of 61 months in 2025. The binding constraint on the AI buildout has moved from capital to electricity, and the people who run the grid now co-set the pace of the race.
A Harvard Chan School-led team's count of 403 US data centers from satellite imagery, published in Nature Sustainability on Nov 16, put the first facility-level number on that demand.
US data centers are on track to use 6.7 to 12 percent of US electricity by 2028, up from 4.4 percent in 2023
The Department of Energy (DOE) announced a report from Lawrence Berkeley National Laboratory (LBNL) that covers all US data centers. It puts them at 4.4% of US electricity in 2023 and projects 6.7-12% by 2028. The same report says data center load tripled over the past decade and is projected to double or triple by 2028. The Nature Sustainability study counted a narrower set, 403 US hyperscale data centers from May 2024 to April 2025, and put them at about 1.8% of US electricity.
The study's upper estimate approaches the annual electricity use of Indiana, Michigan or Tennessee, which is where this week's state-sized headlines come from. Four states (Virginia, Oregon, Ohio and Iowa) hold over half of that use, so the load lands on a few local grids, and new power for those grids has to clear the interconnection queue.
New power took a median of 61 months to connect in 2025
The interconnection queue is where projects ask to connect to the grid. At the end of 2025, 8,244 active projects sat in US queues, and their 2,061 GW of requests exceeds the 1,374 GW of installed US capacity. The requests are mostly new power generation and transmission, so the queue measures how long new supply takes to reach the grid, the supply that data-center demand has to be met with.
Grid operators pace the queue directly. PJM and CAISO, two regional grid operators, show how: PJM paused review of new requests from 2022 until 2026, and CAISO accepted no new requests in 2024 or 2025.
| Clock | Time it runs on |
|---|---|
| Model generation | weeks to months |
| New grid connection | median 61 months in 2025, up from 22 in 2008 |
Even a buildout with committed capital (Anthropic's IPO filing records a $26.0 billion private placement) needs new power that is still waiting in line. Synergy Research estimates that total US data center capacity doubles in the next three years, which is shorter than the median wait to connect new power.
Open the LBNL Queued Up 2026 report and find your region's active queue capacity (the West alone holds 567 GW of requests, ERCOT 408 GW). That is the backlog of new power competing to connect where you live.
FERC, ballot measures and queue pauses have already slowed data-center power
A federal regulator and local voters have each slowed data-center power directly. On Nov 1, 2024, the Federal Energy Regulatory Commission (FERC) voted 2-1 to reject the amended agreement that would have raised Amazon's co-located load at the Susquehanna nuclear plant from 300 to 480 MW.
FERC Commissioner Mark Christie said co-location raises "an array of complicated, nuanced, and multifaceted issues, which collectively could have huge ramifications."
The order means FERC decides how much co-located load a plant can serve, which puts a federal regulator's sign-off ahead of any hyperscaler's power plan.
In the Nov 2026 midterms, voters in 40 of 41 local ballot initiatives nationwide voted to limit or prevent data center development. For a lab choosing where to build, that tally makes local opposition a siting risk it has to price in.
Microsoft contracted a nuclear restart to get power on its own timeline
On Sept 20, 2024, Microsoft signed a 20-year power purchase agreement to restart Three Mile Island Unit 1, also called the Crane Clean Energy Center, with a target of 2028. All of the output goes to Microsoft.
Our read: Unit 1 is an existing plant, so contracting its output skips a multi-year queue request and gives Microsoft a dedicated power source on a timeline it controls.
What to watch as the buildout hits the grid
- PJM's review pause ends. The pause ran from 2022 until 2026, and how fast the backlog moves once reviews restart is the first test of whether such a pause clears a queue. A queue that keeps data centers waiting years keeps lab expansion dates slipping with it.
- FERC Order 2023 implementation. All transmission providers are implementing these interconnection reforms, and LBNL says their effects will not be immediate. Reforms that shorten the wait pull lab timelines forward, and each co-location ruling after the 2-1 Susquehanna order shows how far the veto reaches.
Search your state public utility commission's online docket for "data center" rate cases. If entries appear, note the hearing dates. If none do, try broader terms or ask the commission's docket clerk what large-load cases are open.
How fast AI can scale now depends on how quickly new power gets connected, and grid operators, regulators and local voters hold that schedule.
Sources: Nature Sustainability study (403 facilities, 1.8%, four-state concentration); Harvard Chan School release (1.8% central estimate); Time (Indiana/Michigan/Tennessee comparison, 40 of 41 ballot initiatives, Synergy doubling); DOE announcement of the LBNL 2024 report (4.4% in 2023, 6.7-12% by 2028, load tripling); LBNL Queued Up 2026 (8,244 projects, 2,061 GW vs 1,374 GW, 61/22-month medians, 1 in 5 completion, PJM and CAISO pauses, regional GW, FERC Order 2023); The Register on the FERC order (300 to 480 MW rejection, Christie quote); CNBC and Data Center Dynamics (Microsoft 20-year PPA, 2028 target); Anthropic S-1/A (the $26.0 billion private placement). Current as of Nov 18, 2026.